State updates highway projects

The Ohio Department of Transportation’s weekly report about construction and maintenance work on state highways in area counties:
Hancock County
The U.S. 224 interchange with Interstate 75 is being reconstructed. The project began in February and is expected to be completed late this fall.
• Both the northbound and southbound lanes of I-75 are narrowed and shifted approaching the U.S. 224 interchange.
• Lane restrictions on Interstate 75 will occur during nighttime hours one day of the week, likely today, for pavement repair.
• On June 2 and 3, short-term stops of traffic on Interstate 75 in both directions will occur while setting of bridge beams on the U.S. 224 structure occurs. The stops will occur generally between 8 p.m. and 8 a.m. Both northbound and southbound traffic will be affected on the first night. Only northbound traffic will be affected the second night. Law enforcement will slow and stop traffic approaching the interchange and release traffic once each beam has been set. Traffic will be stopped for up to 20 minutes. Following the beam setting, lane restrictions will continue for the rest of that week both northbound and southbound for overhead work at the bridge. Restrictions will occur between 8 p.m. and 8 a.m.
• Traffic on the U.S. 224 bridge over Interstate 75 is traveling on the north half of the bridge, one lane in each direction with no turn lanes. All ramps at the interchange are currently open.
Elsewhere:
Interstate 75 northbound just north of Ohio 613 will be restricted to one lane through the work zone today for bridge rail repair. The restriction will be in place from 7:30 a.m. to 11 a.m.
Ohio 15 westbound between Western Avenue in Findlay and Ohio 37 will be restricted to one lane through the work zone for sealing of pavement cracks.
U.S. 224 on the east side of Findlay between Plaza Road (Best Buy) and County 236 is occasionally restricted to one lane through the work zone during a traffic signal upgrade project. The new and upgraded signals are in operation. Work on constructing curb ramps and pavement striping is expected to begin during the week.
Ohio 235 pavement repair and resurfacing from County 304 (old U.S. 30) approximately three miles north of Ada to County 313 (old 25) just north of Interstate 75 is now complete.
Ohio 568 between Blanchard Avenue in Findlay and County 180 will be restricted to one lane through the work zone for pavement repair and resurfacing.
Ohio 330 from Ohio 15 to Vanlue High School will be restricted to one lane through the work zone for pavement repair and resurfacing. Paving work has been completed with pavement striping to occur during the week, weather permitting.
Ohio 15 between U.S. 23 in Carey and Ohio 37 in Findlay is restricted to one lane through the work zone for resurfacing. Work is occurring in both the eastbound and westbound direction and will occur during both daytime and nighttime hours during the week.
Hardin County
Ohio 309 from Kenton to Marion will be reduced to one lane through the work zone for sealing of pavement cracks.
U.S. 68 from the Kenton corporation limit to the Logan County line will be reduced to one lane through the work zone for pavement resurfacing. The project is expected to continue through June.
Ohio 235 from Township 150 to County 130 will be restricted to one lane through the work zone for roadside work.
HENRY COUNTY
Ohio 18 resurfacing project: Through August, intermittent lane restrictions are possible on Ohio 18 between Ohio 65 and the Henry/Wood County line, for resurfacing and bridge work. Traffic will be maintained by flaggers.
Ohio 66 bridge repair: From June 10 through July, Ohio 66 between Ohio 2 and Ohio 34 will be closed for bridge repair.
Putnam County
Ohio 109 between Ottawa and the Henry County line will be restricted to one lane through the work zone for pavement repair.
Ohio 634 between Fort Jennings and Continental will be reduced to one lane through the work zone for pavement resurfacing. The project will continue through June.
Ohio 115 one mile south of Vaughnsville will be closed this week for culvert replacement.
SENECA COUNTY
Ohio 12 bridge replacement: Through July, Ohio 12, between Ohio 635 and Ohio 590, will be closed for bridge replacement.
Ohio 18 sewer work: Through June, Ohio 18 between Ohio 101 and South Harley Street is closed for sewer work.
Ohio 19 culvert repair: From today through June, Ohio 19 between County 6 and U.S. 224 will be closed for culvert repair.